Contract Work
* Shoring work (362 piles Ø 600m depth 12m using H beam)
* Piling Work
* 132 piles Ø 1200m depth 34m
* 217 piles Ø 750m depth 23m
* 16 piles Ø 900m depth 24m
* Excavation Work 70,000m3
* Dewatering Work
* Shoring work (362 piles Ø 600m depth 12m using H beam)
* Piling Work
* 132 piles Ø 1200m depth 34m
* 217 piles Ø 750m depth 23m
* 16 piles Ø 900m depth 24m
* Excavation Work 70,000m3
* Dewatering Work